27 Financial Monitoring - March 2010
PDF 146 KB
|
Cabinet Member: |
Leader |
|
|
Forward Plan Ref: |
2009/202 |
|
|
Contact: |
Kathy Wilcox, Principal Financial Manager
Tel: (01865) 323981 |
|
|
Report By: |
Assistant
Chief Executive & Chief Finance Officer |
This is the the tenth
financial monitoring report for the 2009/10 financial year and covers the
period up to the end of January 2010. It
includes projections for revenue, balances, reserves and capital monitoring.
The report sets out
explanations where the forecast revenue outturn is significantly different from
the budget along with proposals to recover the position where appropriate.
The total in – year
Directorate forecast is an overspend of +£4.459m or +1.19% of the latest
budget. After taking into account
supplementary estimates requested in this report, those agreed in February but
not yet reflected in the forecast plus the supplementary estimate for ICT which
requires Council approval in April, the overspend reported this month will
reduce to +£1.484m or +0.4% of the budget.
The current position for
general balances is set out in Annex 5 and shows a forecast of £10.638m after
taking account of agreed and proposed requests for supplementary estimates. After taking into account the forecast
Directorate overspend adjusted for supplementary estimates requested to date
the consolidated revenue balances forecast is £9.154m.
The capital monitoring
position set out in the report shows forecast expenditure for 2009/10 of £88.4m
(excluding schools), a decrease of £1.4m compared to the latest capital
programme.
The Cabinet is
RECOMMENDED to:
(a)
note the report; and
(b)
approve the supplementary estimate request of
£0.425m in relation to winter maintenance in Annex 2f and paragraph 45 and 46.
Additional documents:
Minutes:
Cabinet received the
tenth financial monitoring report (CA6)
for the 2009/10 financial year, covering the period up to the end of January
2010. It included projections for revenue,
balances, reserves and capital monitoring.
The
total in – year Directorate forecast was an overspend of +£4.459m or +1.19% of
the latest budget.
The current position for
general balances showed a forecast of £10.638m after taking account of agreed
and proposed requests for supplementary estimates. After taking into account the forecast
Directorate overspend adjusted for supplementary estimates requested to date
the consolidated revenue balances forecast was £9.154m.
Councillor Zoé Patrick
referred to the supplementary estimate being requested and queried whether this
sum was sufficient in view of the number of pot holes to be mended. Councillor
Rose replied that as the snow melted a sum of had been made available to allow
reactive repairs but it was always envisaged that more work would be required
as the full extent of the damage became known.
The Leader in noting the
current position welcomed that the PCT had been able to address their
commitment to the pooled budgets. The Cabinet Member for Children, Young People
& Families, welcomed Meera Spillett, as the new Director for Children,
Young People & Families and commented that she was already taking steps to
ensure that the Directorate was close to budget.
RESOLVED:
to:
(a)
note the report; and
(b) approve the supplementary
estimate request of £0.425m in relation to winter maintenance in Annex 2f and
paragraph 45 and 46.