78 Provisional Capital Outturn 2022/23
PDF 494 KB
Cabinet Member: Finance
Forward Plan Ref: 2022/251
Contact: Kathy Wilcox, Head of Financial Strategy, 07788302163
Report by Director of Finance (CA7).
a) note the performance
against the capital programme for 2022/23 as set out in the report.
Additional documents:
Decision:
Recommendations approved.
Minutes:
Cabinet received a report on performance relating to the Capital
Programme for 2022/23.
Councillor Calum Miller, Cabinet Member for Finance, presented the
report.
The ten-year Capital Programme set out the agreed capital investment to
deliver the priorities identified in the council’s Capital and Investment
Strategy. The report set out the
performance against the programme shown in the latest monitoring report for 2022/23
and also compared back to the capital programme agreed
by Council in February 2022. The figures
reflected those to be included in the Council’s Statement of Accounts for
2022/23.
The capital programme was updated throughout
the year to reflect the latest delivery profiles and cost estimates for each
programme. The last update was in
January 2023 and this was agreed by Cabinet in March
2023. Expected spend for the year
totalled £184.0m. Actual capital
programme expenditure was £172.2m in 2022/23.
The variation between the latest programme and the actual expenditure
was -£11.8m (-6%). This spend was now
expected to take place in 2023/24.
The capital programme expenditure of £172.2m was funded by £99.1m of
capital grants and other external contributions, £28.8m of developer contributions
and Community Infrastructure Levy, £2.6m of revenue contributions, and £41.7m
of prudential borrowing.
The availability of workforce and materials and inflationary increases
in contract prices were continuing to increase the risk to the deliverability
and cost of capital schemes. The
combined impact of these factors has affected delivery in 2022/23 and is
expected to continue in 2023/24 and future years.
During discussion, members referred to the Council’s priorities for the
development of a sustainable transport infrastructure within the Capital
programme to benefit those areas of the County which were not well served by
transport networks currently.
Councillor Miller moved and Councillor Sudbury seconded the recommendations and they were approved.
RESOLVED to note the
performance against the capital programme for 2022/23 as set out in the report.