167 Capital Programme Monitoring Report - October 2022
PDF 419 KB
Cabinet Member: Finance
Forward Plan Ref: 2022/094
Contact: Kathy Wilcox, Head of Financial Strategy, 07788 302163
Report by Director of Finance (CA8).
Financial Report on capital spending against budget allocations, including any necessary capital programme approvals.
The Cabinet is RECOMMENDED
to:
OCC Capital Programme
1.
Approve the latest capital monitoring position
for 2022/23 (Annex 1) and the associated updated capital programme at Annex 2,
incorporating the changes set out in this report
2.
Note
the approval made under delegated authority of the Leader of the Council for:
a)
New Heyford Primary School (paragraph 26)
b)
Heyford Park School Expansion (paragraph 28)
3.
To
note:
c)
increase of £0.360m to the Active Travel
Programme (Tranche 2) funded from the Budget Priorities Reserve (paragraph 34)
d)
the inclusion of the Department for Transport
(DfT) grant of £32.8m into the capital programme following the Cabinet Report
on 18 October 2022 as funding towards the Zero Emission Bus Regional Area (paragraph
37).
e)
progress on the Structural Maintenance 2022/23
Milestones (Annex 3):
f)
funding of £0.185m towards
the Highway Tree Planting programme funded from the Budget Priorities Reserve (paragraph
52)
Re-profiling
4.
Agree
the in-year re-profiling as identified in the report and (Annex 1 and 2)
Funding
5.
Note
the following grant funding updates and allocations:
a)
Housing & Growth Deal (paragraph 39)
b)
Children Homes (paragraph 66),
c)
Safer Roads (paragraphs 71),
Additional documents:
Decision:
Recommendations approved with one amendment to
recommendation 2: insert “Deputy” before “Leader”.
Minutes:
Cabinet had before
it a report setting out the monitoring position based on activity to the end of
October 2022 - the third update for 2022/23.
It also included an update to the Capital Programme approved by Cabinet
in October 2022 taking into account additional funding
and new and/or changes to schemes.
Councillor Calum
Miller, Cabinet Member for Finance, introduced the report. He highlighted that the total forecast
programme expenditure had reduced by £33.1m compared to the most recently
agreed programme. The largest
contribution to this came from Major Infrastructure projects. The reasons were explained in paragraphs 30
to 35.
On the positive
side, Councillor Miller noted the successes in obtaining £32.8m in government
grants for zero-emission buses and £5.2m matched funding for new children’s
homes. Also, the Department for
Levelling Up, Housing and Communities had confirmed that it will pay the final
£30m instalment of the Housing & Growth Deal and the implications of that
will be outlined in the next report.
Cabinet Members
made the following comments:
·
It was
disappointing that the construction phase of the Wantage Eastern Link Road had
been pushed back to summer 2023 and it was hoped that there would be no further
delays as the housing it was to cater for was well under way.
·
It had
been a major achievement to secure the funding for zero-emission buses and it
was a testament to the Council’s determination to pursue its policies, the hard
work of officers and the partnership working with bus companies.
It was agreed that
recommendation 2 should refer to the “Deputy Leader” rather than the “Leader”.
The recommendations
as amended were proposed by Councillor Miller, seconded by Councillor Phillips and agreed.
RESOLVED to:
OCC Capital Programme
1. Approve the latest capital monitoring position for 2022/23 (Annex 1) and the associated updated capital programme at Annex 2, incorporating the changes set out in this report
2.
Note
the approval made under delegated authority of the Leader of the Council for:
a) New Heyford Primary School (paragraph 26)
b) Heyford Park School Expansion (paragraph 28)
3.
To
note:
c)
increase
of £0.360m to the Active Travel Programme (Tranche 2) funded from the Budget
Priorities Reserve (paragraph 34)
d)
the
inclusion of the Department for Transport (DfT) grant of £32.8m into the
capital programme following the Cabinet Report on 18 October 2022 as funding
towards the Zero Emission Bus Regional Area (paragraph 37).
e)
progress
on the Structural Maintenance 2022/23 Milestones (Annex 3):
f)
funding
of £0.185m towards the Highway Tree Planting programme
funded from the Budget Priorities Reserve (paragraph 52)
Re-profiling
4.
Agree
the in-year re-profiling as identified in the report and (Annex 1 and 2)
Funding
5.
Note
the following grant funding updates and allocations:
a)
Housing
& Growth Deal (paragraph 39)
b)
Children
Homes (paragraph 66),
c)
Safer
Roads (paragraphs 71),