71 Capital Programme Monitoring Report - May 2021
PDF 349 KB
Cabinet Member: Finance
Forward Plan Ref: 2021/020
Contact: Hannah Doney, Head of Corporate Finance Tel: 07584 174654
Report by Director of Finance (CA8).
The report is the first capital programme update and monitoring report for the 2021/22 financial year and focuses on the delivery of the capital programme based on projections at the end of May 2021 and new inclusions within the overall ten-year capital programme.
The Cabinet is
RECOMMENDED to:
a)
agree
the inclusion in the Capital Programme of the following grants funded schemes:
i.
£1.5m
Green Homes Grant programme (Paragraph 27);
ii.
£2.1m
Public Sector De-Carbonisation Grant programme (Paragraph 28),
b)
agree
the inclusion in the Capital Programme of the following schemes:
i.
the
New St Edburg’s expansion to 3 Form Entry Primary
School with a budget of £10.3m funded from s106 contributions (Paragraph 42);
ii.
the
A420 Coxwell Road Junction scheme with a budget of
£1.80m funded from s106 contributions (Paragraph 44),
c)
agree
the increase in the budget for the following schemes:
i.
£2.2m
for the Benson Relief Road scheme funded from Housing & Growth Deal grant
and s106 contributions (Paragraph 46);
ii.
£0.5m
for the Carterton Community Safety Centre funded from s106 contributions
(Paragraph 29),
d)
note
the risk that forward funding of up to £7.0m may be required on the A40 Access
to Witney scheme (Paragraph 48) ahead of receipt of s106 contributions,
e)
approve
the updated Capital Programme at Annex 2 (taking into account
recommendations 1-4)
Additional documents:
Decision:
Recommendations agreed
Minutes:
Cabinet considered the first monitoring report and Capital Programme
update for 2021/22, setting out the monitoring position for 2021/22 based on activity
to the end of May 2021 and providing an update to the Capital Programme
approved by Council in February 2021 to take into account additional funding
and new schemes.
Councillor
Calum Miller drew particular attention to the
increases outlined in paragraphs 3 and 4.
The forecast expenditure for 2021/22 had increased by £3.4m compared to the latest approved capital programme
which was largely due to deferred expenditure from the previous year.
The 10 year Capital
Programme had increased by £49.2m compared to the capital programme approved by
Council in February 2021, due equally to slippage from last year and new grant
funding.
Borrowing for this year was estimated to be £70m some of which was borrowed on behalf of others, such as OxLEP. Councillor Miller thanked officers for their prudent management of borrowing in the past. He referred to the recommended additions to the capital fund, in particular, potential forward funding for the A40 Access to Witney Scheme ahead of the receipt of S106 contributions.
Councillor Miller stated that he was confident that these represented prudent capital investments for the Council and moved the Recommendations.
Councillor Glynis Phillips seconded the proposal.
RESOLVED to:
a)
agree
the inclusion in the Capital Programme of the following grants funded schemes:
i.
£1.5m
Green Homes Grant programme (Paragraph 27);
ii.
£2.1m
Public Sector De-Carbonisation Grant programme (Paragraph 28),
b)
agree
the inclusion in the Capital Programme of the following schemes:
i.
the
New St Edburg’s expansion to 3 Form Entry Primary
School with a budget of £10.3m funded from s106 contributions (Paragraph 42);
ii.
the
A420 Coxwell Road Junction scheme with a budget of
£1.80m funded from s106 contributions (Paragraph 44),
c)
agree
the increase in the budget for the following schemes:
i.
£2.2m
for the Benson Relief Road scheme funded from Housing & Growth Deal grant
and s106 contributions (Paragraph 46);
ii.
£0.5m
for the Carterton Community Safety Centre funded from s106 contributions (Paragraph
29),
d)
note
the risk that forward funding of up to £7.0m may be required on the A40 Access
to Witney scheme (Paragraph 48) ahead of receipt of s106 contributions,
e)
approve
the updated Capital Programme at Annex 2 (taking into account
recommendations 1-4)