66 Capital Programme Monitoring Report - May 2019
PDF 208 KB
Cabinet Member: Finance
Forward Plan Ref: 2019/015
Contact: Katy Jurczyszyn, Strategic Finance Manager (Finance, Strategy & Monitoring) Tel: 07584 909518
Report by Director of Finance (CA7).
The report is the first capital programme update and monitoring report
for the year and focuses on the delivery of the 2019/20 capital programme based
on projections at the end of May 2019 and new inclusions within the overall
ten-year capital programme.
The Cabinet is RECOMMENDED to:
(a)
approve
the updated Capital Programme at Annex 2 and the associated changes to the
programme in Annex 1c;
(b)
approve
the basic need programme up to September 2020 set out in Annex 3;
(c)
approve
the School Structural Maintenance Programme for 2019/20 set out in Annex 4;
(d)
approve
the revised budget provision of £12.750m for the replacement and expansion of
Northfield School project, an increase of £3.250m;
(e)
agree
the inclusion of the Watlington Relief Road project in the Capital programme
with a budget of £12.508m and release of £0.250m for project development;
(f)
approve
the revised budget provision of £16.6m for the Eastern Arc, Access to
Headington scheme, an increase of £1.96m; and
(g)
note
the approvals made under delegated authority of the Leader of the Council for:
i. the revised budget provision of £9.015m
towards the Barton Park new primary School, an increase of £1.8m,
ii. release of £1.8m budget provision towards
the replacement of the Data Centre Infrastructure.
Additional documents:
Decision:
Recommendations agreed.
Minutes:
Cabinet had before it a report which was the first capital programme
update and monitoring report for the year.
The report outlined the delivery of the 2019/20 capital programme based on
projections at the end of May 2019 and new inclusions within the overall
ten-year capital programme.
Councillor Glynis Phillips, Shadow Cabinet Member for Finance, referring
to the outline business case for Barton Park Primary School stated she had queried
where the funding had come from and had been advised that it was from
indexation on the original sum. She sought assurances that similar efforts
would be made in respect of funding for the proposed crossing in her Division.
Referring to additional funds agreed under emergency procedures she queried
whether they could be allocated to individual Cabinet Members for their input
in a structured way.
Councillor Hudspeth, Leader of the Council explained the reasons for
urgency being the need to ensure the school opened in 2020 and that the matter
had been dealt with under normal procedures.
Councillor Roz Smith, local councillor for DIVISION highlighted the
project in her Division noting that officers had warned that there might be the
need for additional costs and design changes as reported in the paper.
Additional off-road parking was required at Hedley Way, but the original design
included a dangerous advisory cycle lane. She was pleased to see the new
design. Councillor Smith thanked officers for taking heed of comments and for
the several briefings.
Councillor David Bartholomew, Cabinet Member for Finance, commented that
when he had become aware of the potential overspend on the project he had
spoken to officers and had been satisfied with the reasons for the additional
costs. It was an example of why money was placed into contingency funds.
Councillor Bartholomew introduced the contents of the report and moved the recommendations.
RESOLVED: to:
(a)
approve
the updated Capital Programme at Annex 2 and the associated changes to the
programme in Annex 1c;
(b)
approve
the basic need programme up to September 2020 set out in Annex 3;
(c)
approve
the School Structural Maintenance Programme for 2019/20 set out in Annex 4;
(d)
approve
the revised budget provision of £12.750m for the replacement and expansion of
Northfield School project, an increase of £3.250m;
(e)
agree
the inclusion of the Watlington Relief Road project in the Capital programme
with a budget of £12.508m and release of £0.250m for project development;
(f)
approve
the revised budget provision of £16.6m for the Eastern Arc, Access to
Headington scheme, an increase of £1.96m; and
(g)
note
the approvals made under delegated authority of the Leader of the Council for:
i. the revised budget provision of £9.015m
towards the Barton Park new primary School, an increase of £1.8m,
ii. release of £1.8m budget provision towards
the replacement of the Data Centre Infrastructure.