125 Capital Programme Monitoring Report - October 2018
PDF 153 KB
Cabinet Member: Finance
Forward Plan Ref: 2018/116
Contact: Katy Jurczyszyn, Strategic Finance Manager (Finance, Strategy & Monitoring) Tel: 07584 909518
Report by Director of Finance (CA7).
The report is the third separate capital programme update and monitoring
report and focuses on the delivery of the 2018/19 capital programme based on
projections at the end of October 2018 and new inclusions within the overall
ten-year capital programme.
The Cabinet is RECOMMENDED to:
(a)
note
the report;
(b)
approve
the updated Capital Programme at Annex 2 and the associated changes to the
programme in Annex 1c; and
(c)
approve
the budget requirement of £6.3m towards the extension of Broadband for Business
in Rural Oxfordshire.
Additional documents:
Decision:
Recommendations agreed.
Minutes:
Cabinet considered the third separate capital programme update and
monitoring report that focussed on the delivery of the 2018/19 capital
programme based on projections at the end of October 2018 and new inclusions within
the overall ten-year capital programme.
Councillor Glynis Phillips, Shadow Cabinet Member for Finance drew
attention to discussion at the Performance and Scrutiny Committee that had
queried the capacity of the Council to manage the large number and scale of
projects to be undertaken; she also referred to the large amount of capital
funding. She commented that additional staff would be required and referred to
the need for a transparent process. Monitoring would be important, and she
hoped that the Council was up to the task. She welcomed the option of borrowing
to build to bring out of county placements for children back in county and
supported selling on any additional places. This needed to be pursued alongside
a long-term strategy to deal with increased demand. On paragraph 17 Councillor Phillips sought
clarification on whether the £17.4m referred to was additional spend. Councillor
Phillips referred to the money allocated to look at a safe pedestrian crossing
on Risinghurst Road. A child had been run over in a
recent incident and she asked whether it was included.
Councillor David Bartholomew, Cabinet Member for Finance, agreed that it
was an ambitious programme requiring sufficient capacity and added that an
awareness of the need to monitor and manage it was high on the agenda. Councillor
Ian Hudspeth, Leader of the Council, commented that capacity was a crucial
issue but that residents would question the Council if it did not put in
ambitious bids to central government. He referred to the HIF bid, which if
accepted would take the capital programme to over £1b.
Councillor Bartholomew referring to building children’s homes was
supportive of the possibility of selling on spare places although there were
obstacles to be overcome. Councillor Bartholomew clarified that there was £10m
already identified for spend on roads and there was an additional £7.4m. Councillor Constance, Cabinet member for
Environment added that in recent discussions with Skanska she had raised with
them their ability to step up in the light of increased investment.
Councillor Bartholomew, introduced the
contents of the report. He drew attention to the recommendation to approve £6.3m
towards the extension of Broadband for Business in Rural Oxfordshire which was
a formality and the project would be fully funded by a grant from DEFRA.
RESOLVED: to:
(a)
note
the report;
(b)
approve
the updated Capital Programme at Annex 2 and the associated changes to the
programme in Annex 1c; and
(c)
approve
the budget requirement of £6.3m towards the extension of Broadband for Business
in Rural Oxfordshire.