1 August 2018
|
Request for exemption from tendering under Contract
Procedure Rule (“CPR”) 20 in
respect of the award of a Works Contract at Matthew Arnold Secondary School
|
Approved an exemption from the tendering requirements
under OCC’s Contract Procedure Rules in respect of the award of a works contract for a Basic Needs
project to provide additional secondary school places at Matthew Arnold
School at a cost of £2,315,920.
|
In order to minimise further
impact on delivery following the collapse of Carillion.
|
|
1 August 2018
|
Request for exemption from tendering under Contract
Procedure Rule (“CPR”) 20 in
respect of the award of a Contract for a Two Classroom Modular Building at Great
Milton CE School
|
Approved an exemption from the tendering requirements
under OCC’s Contract Procedure Rules in respect of the award of a contract for a Two Classroom Modular
Building at Great Milton CE School at a cost of C£180,000.
|
In order to minimise further
impact on delivery following the collapse of Carillion.
|
|
1 August 2018
|
Request for exemption from tendering under Contract
Procedure Rule (“CPR”) 20 in
respect of the award of a Contract to Provide a Basic Need Additional
Primary Expansion of Sutton Courtenay CE Primary School
|
Approved an exemption from the tendering requirements
under OCC’s Contract Procedure Rules in respect of the award of a contract to provide a basic need
additional primary expansion of Sutton Courtenay CE Primary School at a
cost of £394,904
|
In order to minimise further
impact on delivery following the collapse of Carillion.
|
|
1 August 2018
|
Request for
exemption from tendering under Contract Procedure Rule (“CPR”) 20 in
respect of the award of a Contract for Abingdon, Wantage and Oxford Options
Adult Centres
|
Approved an exemption from the tendering requirements
under OCC’s Contract Procedure Rules in respect of the award of a contract for Abingdon, Wantage and
Oxford Options Adult Centres at a cost of £95,522 (£125,522 taking into account a sum set aside for contingency).
|
To avoid significant delays to essential works following
the collapse of Carillion.
|
|
7 August 2018
|
Request for
exemption from tendering under Contract Procedure Rule (“CPR”) 20 in
respect of the award of a Contract for Cross Regional residential and
educational provision for looked after children with complex needs
|
Approved an exemption from the tendering requirements
under OCC’s Contract Procedure Rules in respect of the award of a contract to Broadwood
Residential Limited for Cross
Regional (Oxfordshire, Buckinghamshire, Reading, Bracknell Forest, Milton
Keynes and Hertfordshire) residential and educational provision for
looked after children with complex needs from 1 January 2019 – 31 July 2019
at a cost of £689,619
|
To ensure continuation of service provision during an
exercise to procure residential and educational provision for looked after
children ... view the full minutes text for item 103
|