98 Capital Programme Monitoring Report - August 2018
PDF 160 KB
Cabinet Member: Finance
Forward Plan Ref: 2018/092
Contact: Katy Jurczyszyn, Strategic Finance Manager (Finance, Strategy & Monitoring) Tel: 07584 909518
Report by Director of Finance (CA7).
This is the second separate capital programme update and monitoring
report and focuses on the delivery of the 2018/19 capital programme based on
projections at the end of August 2018 and new inclusions within the overall
ten-year capital programme.
The Cabinet is RECOMMENDED to:
(a)
note
the report;
(b)
approve
the updated Capital Programme at Annex 2 and the associated changes to the
programme in Annex 1c;
(c)
approve
the stage 0 budget requirement of £2.5m towards the expansion at Radley School within the Basic Need Programme with funding
options considered at Stage 1 gateway.
(d)
approve
the stage 0 budget requirement of £1.5m towards the expansion at Bardwell
School within the Basic Need Programme.
(e)
approve
the additional budget requirement of £3.5m towards the Eastern Arc Phase 1:
Access to Headington Project, for an overall budget
provision of £14.5m.
Additional documents:
Decision:
Recommendations agreed.
Minutes:
Cabinet considered
a capital programme update and monitoring report that focussed on the delivery
of the 2018/19 capital programme based on projections at the end of August 2018
and new inclusions within the overall ten-year capital programme.
Councillor
Phillips, Shadow Cabinet Member for Finance, commented that the report reflects
the amount of activity taking place. Referring to the annexes which listed
projects she noted that the Risinghurst project did not seem to be there.
Councillor Phillips highlighted the Access to Headington project and asked
Cabinet to support the recommendation. She added that the issue had been the
piecemeal approach to the project with works since October 2016 and a further
phase still outstanding. Councillor Phillips queried confidence levels that the
Council had the capacity and confidence to manage this level of activity.
Councillor
Bartholomew responded to the points made noting that it was not always possible
to get all the money for a project together at one time. In reality schemes
were ready to go and the Council sought funding where ever they could. Capacity
was being addressed at every level with people being brought. In addition the
capacity of contractors was being addressed. Councillor Hudspeth, Leader of the
Council added that he had complete confidence in officers to monitor the
programme. It was good to have such a robust capital programme. It was an
exciting time for Oxfordshire to be in a position to deliver the infrastructure
everyone wants.
Councillor
Bartholomew, introduced the contents of the report and moved the
recommendations.
RESOLVED:-
(a)
note
the report;
(b)
approve
the updated Capital Programme at Annex 2 and the associated changes to the
programme in Annex 1c;
(c)
approve
the stage 0 budget requirement of £2.5m towards the expansion at Radley School
within the Basic Need Programme with funding options considered at Stage 1
gateway.
(d)
approve
the stage 0 budget requirement of £1.5m towards the expansion at Bardwell
School within the Basic Need Programme.
(e) approve the additional budget requirement of £3.5m towards the Eastern Arc Phase 1: Access to Headington Project, for an overall budget provision of £14.5m.