Issue details

Speedwell House Early Works Package

The Speedwell House project was re-baselined for both cost and programme against the revised scope in November 2025 (refurbishment and remodelling of existing building). The revised design avoids work in the ground therefore removes the risk of archaeology discovery.
To achieve both budget and programme it has been determined that an Early Works package needs to be instructed to enable construction work to commence early and in advance of full business case approval.


The key benefits to the instruction of these early works include avoidance of a delay of up to 4 month to completion, and, placing early orders for several large packages will help to reduce the impact of inflation caused by the Middle East situation.

Decision type: Key

Reason Key: - Capital Expenditure > £2m;

Decision status: For Determination

Notice of proposed decision first published: 03/08/2026

Decision due: 4 Sep 2026 by Delegated Decisions by Cabinet Member for Finance, Property and Transformation

Lead member: Cabinet Member for Finance, Property and Transformation

Lead director: Director of Property & Assets

Contact: Will Pleeth, Consultant Project Lead - Property and Assets Email: will.pleeth@oxfordshire.gov.uk, David Scrimgeour, Senior Cost Manager, Property and Assets Email: david.scrimgeour@oxfordshire.gov.uk.

Consultation process

Change Request in draft for submission to Property Portfolio Board in August 2026

Consultees

Legal Services; Finance; Estates

Plan Reference: 26/183

Reason No Public Access: None